- 2014 roadmap goal of 52 cents per watt at the panel level -- accomplished through efficiency gains and improvements in throughput
- 14% module efficiency in 2014
- Capex at 65 cents per watt factory capacity.
- It takes only 2.5 hours for the factory to go from glass to module
- 2012 production capacity will be 2 gigawatts
- Energy Payback Time (EPBT) is .65 .8 years (EPBT includes manufacturing and installation). Garabedian challenged the silicon guys to lower their silicon consumption to keep up with the First Solar EPBT.
- Q1 conversion efficiency was 11.1 percent, Q1 manufacturing cost was 81 cents per watt, Q1 revenue was $568 million
"Solar Energy is a clean and free natural resource, available to the mankind. The effective use of this un-tapped energy resource has huge potential to develop every corner of the globe, and establish a peaceful, safe and pleasant world for our future generations. It is our responsibility to start this onerous but honorable task"
Friday, June 18, 2010
First Solar Continues to Raise the Performance Bar : Greentech Media
First Solar Continues to Raise the Performance Bar : Greentech Media